Hi every one.
May some one can help for the right design to manage the WIP control.
There is are three process stages A, B & C.
* Process A to produce certain Qty of a product as table given below and entered data via FrmA:
TblA
ID
PrdnDate
CartNo
Product
Qty
Transferred (Yes/No) *Default Value "Yes"
Notes
* Process B to hold the qty being produced by Process A for certain days and major information required to be:
CartNo
PrdnDate
Product
Qty
* Process C to use the quantities as required and data entry to be used by selecting the CartNo from combobox via FrmC and make inspection of the Qty either good or rejected.
Requirements:
a. How to have central Process B WIP record? Which is produced by A but being not utilized yet from Process C?
b. If the CartNo is selected via combobox at FrmC then it should not be any more available in Process C WIP record.
How these two requirements can be met from the above scenario.
Regards