I have found some solutions to this online. However, my problem is that these have all been for a typical 5 day work week.
I have two criteria that I am not sure how to address in order for it to work how I would like.
1. We don't work a typical work week. Every other week is a 4 day work week.
2. I need to pull the dates from a table. Just wasn't sure how to enter those into the code using the correct syntax.
https://msdn.microsoft.com/en-us/lib...ice.12%29.aspx
This is the code that I was thinking about using as a guide to calculate the workdays.
Suggestions on how to change it to fit my criteria
Thanks ahead of time.